When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
A) The smallest LS of all its immediate successor activities to establish the LF.
B) The largest ES of all its immediate successor activities to establish the LF.
C) The average LS of all its immediate successor activities to establish the LF.
D) The smallest ES of all its immediate successor activities to establish the LF.
E) The largest LS of all its immediate successor activities to establish the LF.
Correct Answer:
Verified
Q24: A _ activity is one that has
Q27: Tom is responsible for ordering hardware for
Q28: The likelihood the original critical path(s)will change
Q31: A _ activity is one that has
Q33: The minimum amount of time a dependent
Q41: If testing cannot be completed any earlier
Q43: System documentation cannot end until three days
Q47: Which of the following will correctly calculate
Q49: If, for some reason, the project must
Q54: Which of the following is true about
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents