The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
A) Detailed WBS work package estimates.
B) Template method.
C) Function point method.
D) Time-phased cost estimates.
E) Phase estimating.
Correct Answer:
Verified
Q25: Typical kinds of costs found in a
Q26: Which of the following would best represent
Q27: Refining estimates may be necessary for a
Q31: Large projects that have long time horizons
Q32: Benefits of Reference Class Forecasting include
A)Acting as
Q33: Estimating can be challenged by
A)Human Nature.
B)Political dynamics.
C)Difficulty
Q34: While it may be true that Mega
Q35: The pattern of improvement identified from a
Q42: Which of the following is NOT one
Q59: Companies are using which of the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents