Question 21
True/False
A straight-line flow pattern is considered a good layout design for back-office service operations.
Question 22
True/False
A manufacturing cell groups the same or similar machines into cells to work on products that have dissimilar shapes and dissimilar processing requirements.
Question 23
Multiple Choice
Using the assembly-line balancing procedure, which of the following is the required cycle time if the production time in minutes per day is 1,440 and the required output per day in units is 2000?
Question 24
True/False
Having a lot of interstage storage of materials is considered a good layout design for a manufacturing plant.
Question 25
Multiple Choice
Which of the following is not considered an input to the layout decision in facility layout analysis?
Question 26
True/False
As a general rule, manufacturing workstations should not be very close together.
Question 27
Multiple Choice
Which of the following basic types of production layout formats is one that has similar equipment or functions are grouped together?
Question 28
Multiple Choice
Which of the following basic types of production layout formats is one in which equipment or work processes are arranged according to the progressive steps by which the product is made?
Question 29
Multiple Choice
Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units?
Question 30
Multiple Choice
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3, and 6 minutes, and the cycle time is 8 minutes?
Question 31
Multiple Choice
Which of the following is not a basic type of production layout format?
Question 32
True/False
The objective of a retail service layout is to maximize net profit per square foot of store space.
Question 33
True/False
In a good layout design for a manufacturing facility, it is acceptable to have backtracking by personnel in the delivery of a customer's product.
Question 34
Multiple Choice
You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure.The cycle time of the line is 5 minutes, and the sum of all that tasks required on the line is 25 minutes.Which of the following is the correct value for the resulting line's efficiency?
Question 35
Multiple Choice
Which of the following is a basic type of production layout format?
Question 36
True/False
A project layout is characterized by a relatively low number of production units in comparison with workcenter and assembly-line formats.
Question 37
True/False
Assembly-line balancing means assigning all necessary tasks to a series of workstations so that each workstation has no more than can be done in the workstation cycle time and so that idle time across all workstations is minimized.
Question 38
Multiple Choice
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?