Consider the Following Work Breakdown Structure What Is the Estimated Slack Time for Activity E?
A)
Consider the following work breakdown structure: What is the estimated slack time for activity E?
A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks
Correct Answer:
Verified