Which of the following leads to simulation being a useful tool with uncertain activity times?
A) paths that are not independent
B) activity times that are not deterministic
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates
Correct Answer:
Verified
Q111: Consider the project depicted by the following
Q112: Consider the following work breakdown structure:
Q113: Activity E has an optimistic time of
Q114: Consider the following work breakdown structure:
Q115: Consider the following work breakdown structure:
Q117: Determine the amount of slack in
Q118: Consider the following work breakdown structure:
Q119: Consider the following work breakdown structure:
Q120: Using the information given in the
Q121: Consider the following work breakdown structure:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents