Question 1

Multiple Choice

The master budget contains the following components, among others: direct-material budget, budgeted balance sheet, production budget, and cash budget. Which of these components would be prepared first and which would be prepared last?


A) Direct-material budget, cash budget
B) Direct-material budget, balance sheet
C) Production budget, cash budget
D) Production budget, balance sheet
E) Cash budget, direct-material budget

Correct Answer: