Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by one day what is the total time of the project and total cost?
A) Total time is 13 days,total cost is $1,500
B) Total time is 12 days,total cost is $2,000
C) Total time is 12 days,total cost is $2,300
D) Total time is 11 days,total cost is $1,850
E) Total time is 11 days,total cost is $2,350
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q76: Describe how CPM handles the trade-offs between
Q80: If the pessimistic duration of an activity
Q81: An assumption of three-activity-time CPM analysis is
Q82: Below are the data for a Time-Cost
Q84: Which of the following is an assumption
Q86: If the pessimistic duration of an activity
Q88: Below are the data for a
Q89: You have collected the data for
Q90: You have collected the data for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents