You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200 and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:
Verified
Q64: You know when you have arrived at
Q70: What are "project milestones?" _
Q73: What is that sequence of activities that
Q76: Describe how CPM handles the trade-offs between
Q77: What is the criterion for determining whether
Q85: Below are the data for a
Q86: If the pessimistic duration of an activity
Q88: Below are the data for a
Q89: You have collected the data for
Q95: You have collected the data for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents