The Relationship Between the Aggregate Plan and Master Production Schedule

Question 42

Multiple Choice

The relationship between the aggregate plan and Master Production Schedule (MPS) is:


A) The aggregate plan balances the plant's capacity with demand and the MPS translates this plan into numbers of specific products in time frames
B) The aggregate plan is for 6 months and the MPS is for 3 months
C) The aggregate plan uses simulation and the MPS uses regression analysis
D) The MPS calculates labor time and the aggregate calculates labor and material
E) MPS starts with macro units and the aggregate plan starts with micro units

Correct Answer: