Multiple critical paths can exist under the critical path method (CPM) because:
A) There is more than one way to complete the project
B) Different network paths can have the same total time
C) Great flexibility of activity sequences is available
D) None of the above
Correct Answer:
Verified
Q4: Which of the following statements is true
Q8: An assumption of the PERT method is:
A)Activity
Q9: Project managers' objectives include:
A)Cost
B)Quality
C)Flexibility
D)All of the above
Q10: Controlling a project does NOT include:
A)Monitoring costs,time,and
Q11: Project management requires:
A)Scheduling,planning,and controlling
B)Quantitative skills
C)Behavioral skills
D)All of
Q12: A network-based project scheduling method that requires
Q14: "Slack" refers to the difference between:
A)Late and
Q15: Which of the following statements is NOT
Q16: The critical path of the following network
Q17: Gantt charts are effective for project scheduling
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents