Given the List of Activities,the Expected Time Estimates,and Variances,compute the Probability

Question 7

Multiple Choice

Given the list of activities,the expected time estimates,and variances,compute the probability that the project time will be less than 30 minutes.Round Z to two decimals.  Given the list of activities,the expected time estimates,and variances,compute the probability that the project time will be less than 30 minutes.Round Z to two decimals.    \begin{array}{ll} \text { Activity } & \mathrm{T}_{e} \text { (minutes)  }&\text { Variance } \\ \text { A } & 2.00&0.5 \\ \text { B } & 6.17&1.75 \\ \text { C } & 8.34&1.45 \\ \text { D } & 10.05&3.00 \end{array}  A) 0.6950 B) 0.7500 C) 0.8907 D) 0.9082 E) 0.9989
 Activity Te (minutes)   Variance  A 2.000.5 B 6.171.75 C 8.341.45 D 10.053.00\begin{array}{ll}\text { Activity } & \mathrm{T}_{e} \text { (minutes) }&\text { Variance } \\\text { A } & 2.00&0.5 \\\text { B } & 6.17&1.75 \\\text { C } & 8.34&1.45 \\\text { D } & 10.05&3.00\end{array}


A) 0.6950
B) 0.7500
C) 0.8907
D) 0.9082
E) 0.9989

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents