____ occur when two or more activities follow a single node.
A) Combinations
B) Conflicts
C) Merges
D) Bursts
Correct Answer:
Verified
Q37: _ involves estimating the number of work
Q38: The critical path always includes the most
Q39: Most projects have one path through a
Q40: Many projects,especially in information technology,have very unrealistic
Q41: In a _ relationship,the "from" activity must
Q43: In a _ relationship,the "from" activity cannot
Q44: _ results in supporting detail to document
Q45: _ dependencies are inherent in the nature
Q46: _ is the amount of time an
Q47: _ provide(s)a standard format for displaying project