In a ____ relationship,the "from" activity cannot start until the "to" activity is started.
A) start-to-start
B) finish-to-start
C) finish-to-finish
D) start-to-finish
Correct Answer:
Verified
Q38: The critical path always includes the most
Q39: Most projects have one path through a
Q40: Many projects,especially in information technology,have very unrealistic
Q41: In a _ relationship,the "from" activity must
Q42: _ occur when two or more activities
Q44: _ results in supporting detail to document
Q45: _ dependencies are inherent in the nature
Q46: _ is the amount of time an
Q47: _ provide(s)a standard format for displaying project
Q48: The _ is a network diagramming technique