Using the assembly-line balancing procedure,which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7,4,7,8,9,4,3 and 6 minutes,and the cycle time is 8 minutes?
A) 3
B) 5
C) 6
D) 8
E) None of the above