Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?
A) Total time is 10 days,total cost is $2500
B) Total time is 9 days,total cost is $2300
C) Total time is 8 days,total cost is $2750
D) Total time is 8 days,total cost is $1850
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q67: You have just performed a CPM analysis
Q69: You have collected the data for
Q70: Below are the data for a
Q70: What are "project milestones?" _
Q73: What is that sequence of activities that
Q75: Below are the data for a
Q76: Describe how CPM handles the trade-offs between
Q76: You have collected the data for
Q77: Below are the data for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents