Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by one day what is the total time of the project and total cost?
A) Total time is 13 days,total cost is $1500
B) Total time is 12 days,total cost is $2000
C) Total time is 12 days,total cost is $2300
D) Total time is 11 days,total cost is $1850
E) Total time is 11 days, total cost is $2350
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q67: You have just performed a CPM analysis
Q69: You have collected the data for
Q70: Below are the data for a
Q70: What are "project milestones?" _
Q72: Below are the data for a
Q73: What is that sequence of activities that
Q75: Below are the data for a
Q76: You have collected the data for
Q76: Describe how CPM handles the trade-offs between
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents