Spruce Bank is planning to automate some of its back office functions and reduce operating costs. The installation of new computers and software will require an initial investment of $1,000,000. The savings generated because of reduced personnel cost is $200,000 per year. The bank uses an 8 percent rate of discount to evaluate cost saving projects which are expected to last 10 years.
-The maximum cost savings that can be generated with this new equipment has been estimated to be $264,237. In order to accept this project, what is the minimum number of years the projected savings must be realized before the project breaks even?
A) 3.7 years.
B) 4.7 years.
C) 5.7 years.
D) 6.7 years.
E) 7.7 years.
Correct Answer:
Verified
Q90: Suppose that the doubling of a bank's
Q98: A new computer system is expected to
Q100: As of January 2012, which of the
Q101: Spruce Bank is planning to automate some
Q102: Spruce Bank is planning to automate some
Q103: Choose among the following services provided by
Q104: The following information is available on the
Q105: The following information is available on the
Q106: The following information is available on the
Q107: Spruce Bank is planning to automate some
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents