What variance does the difference between the actual cost of the direct labour hours worked and the planned cost of the direct labour hours measure?
A) The direct labour efficiency variance.
B) The direct labour rate variance.
C) The total direct labour variance.
D) None of the above.
Correct Answer:
Verified
Q62: Use the information below to answer
Q63: Where there is an insignificant adverse variance,
Q64: If budgeted profit is $11,000, favourable variances
Q65: Prepare a flexible cost budget for
Q66: An adverse (unfavourable)labour efficiency variance could be
Q68: Where budget targets have proven to be
Q69: Which budget criticism can be dealt with
Q70: Where there is a significant favourable variance
Q71: Budget targets should be:
A)unachievable so that there
Q72: Use the information below to answer
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents