Percentage-of-completion and completed-contract methods
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:
Instructions
Calculate how much gross profit that Lion should recognize each year, assuming:
Method Used For 2020 For 2021
a) Completed contract
b) Percentage-of-completion
Correct Answer:
Verified
Q107: Consignment sales
On July 2, Cardinal Corp. ships
Q108: Explain what a bill-and-hold sale is and
Q109: Percentage-of-completion and completed-contract methods
On January 1,
Q110: Consignment sale
In 2020, the following transaction
Q111: Explain the advantages and disadvantages of the
Q112: Long-term construction project accounting
Giants Construction Inc.
Q113: Coquel Company has a non-cancellable contract
Q114: Percentage-of-completion method
Flames Corp. contracted to build
Q115: Accounting for long-term construction contracts
The
Q116: Completed-contract method
Broncos Construction Ltd. reported the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents