A&C Distributors is a company that represents many outdoor products companies and schedules deliveries to discount stores,garden centers,and hardware stores.Currently,scheduling needs to be done for two lawn sprinklers,the Water Wave and Spring Shower models.Requirements for shipment to a warehouse for a national chain of garden centers are shown below.
Let Sij be the number of units of sprinkler i shipped in month j,where i = 1 or 2,and j = 1,2,or 3.Let Wij be the number of sprinklers that are at the warehouse at the end of a month,in excess of the minimum requirement.
a Write the portion of the objective function that minimizes shipping costs.
b.An inventory cost is assessed against this ending inventory.Give the portion of the objective function that represents inventory cost.
c.There will be three constraints that guarantee,for each month,that the total number of sprinklers shipped will not exceed the shipping capacity.Write these three constraints.
d.There are six constraints that work with inventory and the number of units shipped,making sure that enough sprinklers are shipped to meet the minimum requirements.Write these six constraints.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: The primary limitation of linear programming's applicability
Q2: A decision maker would be wise to
Q12: A company makes two products, A and
Q13: For the multiperiod production scheduling problem in
Q15: Compared to the problems in the textbook,real-world
Q24: National Wing Company (NWC)is gearing up for
Q26: Larkin Industries manufactures several lines of decorative
Q30: Information on a prospective investment for Wells
Q32: The Meredith Ribbon Company produces paper and
Q51: Winslow Savings has $20 million available for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents