The path in a project network with the average duration is the critical path
Correct Answer:
Verified
Q14: An activity in a project network cannot
Q15: The earliest start of an activity is
Q16: The latest starting time for an activity
Q18: The project network diagram describes sequential relationships
Q20: The values assigned to the nodes in
Q21: The earliest finish time for an activity
Q21: The slack of an activity is the
Q22: If an activity is not on the
Q23: Activities that are not on the critical
Q27: Only activities on the critical path are