The latest starting time for an activity is equal to the latest finish time minus the duration of the activity
Correct Answer:
Verified
Q11: In PERT,the project duration will never exceed
Q12: The length of the critical path is
Q13: Project managers must often function in an
Q14: An activity in a project network cannot
Q15: The earliest start of an activity is
Q18: The project network diagram describes sequential relationships
Q19: The path in a project network with
Q20: The values assigned to the nodes in
Q21: The earliest finish time for an activity
Q21: The slack of an activity is the