What is the probability that the critical path will be completed within 210 days?
A) 0 5000
B) 0 8413
C) 0 9544
D) 0 9772
E) 0 9987
Correct Answer:
Verified
Q82: At which point does crashing of a
Q83:
-What is the probability that the
Q84: In crashing a project,a manager will generally
Q85:
-What is the estimated standard deviation
Q86: When using linear programming to make crashing
Q87:
-What is the estimated mean time
Q88: The project management strategy of injecting additional
Q90:
-What is the estimated mean time
Q91: PERT/Cost:
A)finds the penalty costs if a project
Q115: What is the estimated slack time for