A manufacturer's average work-in-process inventory for Part 1234 is 1,250 parts. The workstation produces parts at the rate of 150 parts per day. What is the average amount of time a part spends at the workstation?
A) More than 4 but less than or equal to 6 days
B) More than 6 but less than or equal to 8 days
C) More than 8 but less than or equal to 10 days
D) More than 10 days
Correct Answer:
Verified
Q46: Which of the following statements is TRUE
Q47: A car rental company at a major
Q48: A wealth management company is able to
Q49: A car rental company at a major
Q50: The average number of entities completed per
Q52: Projects are often used for standardized products
Q53: Job shop processes use flexible, general purpose
Q54: A custom good or service is produced
Q55: The average number of hotel rooms occupied
Q56: An accounting firm is capable of processing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents