Question 41
True/False
The product-process matrix works well for both goods and services.
Question 42
Multiple Choice
A custom machine shop is able to process 25 orders per day. The average processing time is 4 days. What is the average number of orders that are in process at any time?
Question 43
True/False
Flow shop processes are more rigid and highly specialized than continuous flow processes.
Question 44
True/False
Configurations of standard parts, subassemblies, or services that can be selected by customers from a limited set are called make-to-order goods and services.
Question 45
True/False
Standard goods are made in anticipation of customer demand and stocked in inventory and therefore, are usually available,
Question 46
Multiple Choice
Which of the following statements is TRUE about Little's Law?
Question 47
Multiple Choice
A car rental company at a major airport has an average inventory of 48 cars rented. Cars are rented for an average of 3 days. How many rentals are processed each day on average?
Question 48
Multiple Choice
A wealth management company is able to process 300 customer statements (bills) per day. The average processing time is six (6) days. What is the average number of statements (bills) the company has in process at any time?
Question 49
Multiple Choice
A car rental company at a major airport has 70% of its fleet of 200 cars rented each day on average. Cars are rented for an average of 4 days. How many rentals are processed each day on average?
Question 50
Multiple Choice
The average number of entities completed per unit time-the output rate-from a process is called _____.
Question 51
Multiple Choice
A manufacturer's average work-in-process inventory for Part 1234 is 1,250 parts. The workstation produces parts at the rate of 150 parts per day. What is the average amount of time a part spends at the workstation?