Perform a capacity analysis of the process given below and answer questions #16, #17, and #18 to help fix the process. The numbers in parenthesis (#) are the time in minutes to complete one unit of work. Demand on the process averages 27 units per hour and each unit must be worked on by all five stages. Administrative clerks do Stages A and B. The assistant manager does Stages D and E. The coding specialist does Stage C.
SHAPE \* MERGEFORMAT
-The total process (throughput) capacity in units per hour for the five stage process, A to D, assuming 3 administrative clerks, 2 coding specialist, and 4 assistant managers on duty is:
A) less than 10 units per hour.
B) more than 10 units but less than or equal to 20 units.
C) more than 20 units but less than or equal to 30 units.
D) more than 30 units but less than or equal to 40 units.
Correct Answer:
Verified
Q15: Safety capacity or a capacity cushion is
Q16: Perform a capacity analysis of the process
Q17: Steve, an operations manager at Clan Corp.
Q18: Safety capacity is most closely related to
Q19: C&M Machining is developing plans for a
Q21: A medical equipment testing and calibration
Q22: The job that represents the bottleneck in
Q23: _ strategy matches the capacity additions with
Q24: _ is a strategy that waits until
Q25: A firm will encounter short periods of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents