The bill of material (BOM) for Products A and B are shown below followed by a table of inventory data (called Exhibit 1) . The master production scheduling (MPS) for A calls for 150 units of A to be completed in Week 4 and another 225 units to be completed in Week 5. End item A has a two-week lead time. The MPS calls for 400 units of B to be completed in Week 6. End item B has a one-week lead time. Exhibit 1
____________________________________________________________________
-Using the data in Exhibit 1, determine the timing and amount of the first planned order receipt for Item C.
A) Week 3; 800 units
B) Week 3; 645 units
C) Week 3; 1,600 units
D) Week 2; 800 units
Correct Answer:
Verified
Q12: Aggregate planning:
A) is not driven by forecasts.
B)
Q13: A paint company has the following
Q14: A company currently has no items in
Q15: The Academic Company mixes and bottles
Q16: The Academic Company mixes and bottles
Q18: The bill of material (BOM) for
Q19: If A has a gross requirement to
Q20: Which of the following is least likely
Q21: Which of the following is an aggregate
Q22: _ are the total demand for an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents