The Following Five Jobs, Along with Their Processing Time and Due

Question 19

Multiple Choice

The following five jobs, along with their processing time and due dates, are given below.
 Processing  Days Due  Job  Time (days)   From Today  A 812 B 49 C 36 D 77 E 520\begin{array}{|l|l|l|}\hline & \text { Processing } & \text { Days Due } \\\hline \underline{\text { Job }} & \underline{\text { Time (days) }} & \text { From Today } \\\hline \text { A } & 8 & 12 \\\hline \text { B } & 4 & 9 \\\hline \text { C } & 3 & 6 \\\hline \text { D } & 7 & 7 \\\hline \text { E } & 5 & 20 \\\hline\end{array}

-Using the earliest due date (EDD) rule, the average lateness for the five jobs is _____.


A) less than or equal to 5 days
B) more than 5 but less than or equal to 10 days
C) more than 10 but less than or equal to 15 days
D) more than 15 but less than or equal to 20 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents