The county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is TRUE?
A) The expected duration of the project is 30 + 22 + 16 = 68 days.
B) Path A-B-C-H is the critical path.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
Correct Answer:
Verified
Q7: Which of the following is NOT a
Q8: The Baker county government has decided to
Q9: _ is the sequence of activities that
Q10: Consider the following project network. Time
Q11: A Gantt chart is:
A) a useful tool
Q13: In which stage of the project life
Q14: Slack in an activity is computed as:
A)
Q15: Jude is in charge of the
Q16: A project has three parallel paths. A-B-C
Q17: Which of the following is NOT considered
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents