The Baker county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The critical path method (CPM) project has three sequential (in series, that is "i" is first, then "ii" and finally "iii.") paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 10 days, (ii) path G-J-K-L to install sidewalks with handicap capabilities that takes 20 days, and (iii) path U-V-Z-W to repave the street including storm drains that takes 8 days. Which one of the following statements is true?
A) The expected duration of the project is 10 + 20 + 8 = 38 days.
B) The expected duration of the project is 20 days.
C) The normal time is inversely related to the crash time.
D) The three sub-system precedent relationships are in parallel.
Correct Answer:
Verified
Q3: Jude is in charge of the
Q4: Consider the following project network. Time
Q5: Which one of the following is NOT
Q6: Which one of the following skills contributes
Q7: Which of the following is NOT a
Q9: _ is the sequence of activities that
Q10: Consider the following project network. Time
Q11: A Gantt chart is:
A) a useful tool
Q12: The county government has decided to redo
Q13: In which stage of the project life
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents