A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
Solutions are at the end of questions
-The probability that the project will take longer than 28 weeks to complete is _____.
A) less than or equal to 0.1
B) greater than 0.1 but less than or equal to 0.3
C) greater than 0.3 but less than or equal to 0.6
D) greater than 0.6 but less than or equal to 0.9
Correct Answer:
Verified
Q60: Rose is in charge of the
Q61: In the Activity-On-Node (AON) network, the nodes
Q62: Activity times are always estimated from historical
Q63: Preparation of annual reports does not require
Q64: Strong leadership is an impediment to project
Q66: In most organizations, projects cut across organizational
Q67: Which one of the following statements about
Q68: All activities on the critical path have
Q69: Immediate predecessors are activities that must be
Q70: The early start time for an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents