Which one of the following statements about Project Evaluation and Review Technique (PERT) is TRUE?
A) The expected time is given and not computed using formulas.
B) The probability of completing the project on time is 0 when the project target completion time equals the expected time.
C) The normal probability distribution is not used in PERT methods.
D) The variance in project duration is given by the sum of the variances of the critical path activities.
Correct Answer:
Verified
Q62: Activity times are always estimated from historical
Q63: Preparation of annual reports does not require
Q64: Strong leadership is an impediment to project
Q65: A high definition television manufacturer in
Q66: In most organizations, projects cut across organizational
Q68: All activities on the critical path have
Q69: Immediate predecessors are activities that must be
Q70: The early start time for an activity
Q71: To compute the critical path, all nodes
Q72: Project managers need to be specialists, not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents