Question 21
Multiple Choice
Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed: Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for purchasing in an activity-based performance report?
Question 22
Multiple Choice
Glenn, SA., has done a cost analysis for its production of T-shirts. The following activities and cost drivers have been developed: Following are the actual costs of producing 75,000 T-shirts: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for setups in an activity-based performance report?
Question 23
Multiple Choice
Villafane, SA., has done a cost analysis for its production of decals. The following activities and cost drivers have been developed: Following are the actual costs of producing 35,000 decals: 1,000 machine hours; 5 batches; 30 purchase orders
The following variances were given in the activity performance report:
What is the activity variance for purchasing?
Question 24
Multiple Choice
The budget most appropriate for control purposes is the
Question 25
Multiple Choice
Glenn, SA., has done a cost analysis for its production of T-shirts. The following activities and cost drivers have been developed: Following are the actual costs of producing 75,000 T-shirts: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for purchasing in an activity-based performance report?
Question 26
Multiple Choice
Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed: Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for total costs in an activity-based performance report?
Question 27
Multiple Choice
Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed: Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for maintenance in an activity-based performance report?
Question 28
Multiple Choice
The static budget variance for materials is £200 F and the budgeted cost for materials is £52,000. If the budgeted volume is 13,000 and the actual volume is 13,500, then the flexible budget variance is
Question 29
Multiple Choice
Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed: Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for setups in an activity-based performance report?
Question 30
Multiple Choice
If production was budgeted at 400 units and the actual production was 420 units, what would be the static budget variance for materials if the actual cost of materials was £4,150 and the budgeted cost per unit is £10?