An assembly line with 28 activities is to be balanced.The total amount of time required for all 28 activities is 39 minutes.The longest activity is 2.2 minutes and the shortest is 0.8 minutes.The line will operate for 450 minutes per day.What is the assembly line efficiency with 11 stations and a product produced every 5 minutes?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q64: A company is setting up an assembly
Q65: A product requires the following tasks to
Q67: For the following assembly line data, balance
Q68: The twelve tasks necessary to assemble a
Q70: A small electronics company assembles power supplies
Q71: An assembly line with 28 activities is
Q72: Consider the following assembly line information for
Q73: An assembly line with 28 operations is
Q74: In your first job you must set
Q84: Explain the sociotechnical approach to job design
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents