Solved

The Actual Cost of Direct Labour Per Hour Is $13

Question 135

Multiple Choice

The actual cost of direct labour per hour is $13.00. Two standard direct labour hours are allowed per finished good. During the current period, 2,000 finished goods were produced using 3,800 direct labour hours. The direct labour efficiency variance is $1,300, favourable. Calculate the standard direct labour rate per hour.


A) $26.00
B) $6.50
C) $13.00
D) $10.00

Correct Answer: