Green Garden Supply budgeted three hours of direct labour per unit at $10.00 per hour to produce 500 units of product. The 500 units were completed using 1,600 hours of direct labour at $10.50 per hour.
-What is the direct labour efficiency variance at Green Garden Supply?
A) $1,000 unfavourable
B) $1,000 favourable
C) $1,050 unfavourable
D) $1,050 favourable
Correct Answer:
Verified
Q127: Custom Tile Works budgeted 2.5 hours of
Q128: Gutierrez Company budgeted 10,000 kilograms of direct
Q129: At Sandra's Sewing Company the actual cost
Q130: At Sandra's Sewing Company the actual cost
Q131: Grayson Industries has collected the following data
Q133: Grayson Industries has collected the following data
Q134: Thomas Corporation produces stopwatches. According to company
Q135: The actual cost of direct labour per
Q136: Grayson Industries has collected the following data
Q137: The actual cost of direct materials is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents