A Sheet Metal Company Has Developed the Following Six-Month Production

Question 73

Essay

A sheet metal company has developed the following six-month production schedule in thousands of square (yards):
 Week 123456 Metal 150100175200160160\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Metal } & 150 & 100 & 175 & 200 & 160 & 160 \\\hline\end{array}
In addition, their monthly labor and machine capacities in hours) available, and the production standards in hours per square yard) are:
abor Machine  Capacity Available 16,00020,000 Prnduction Standard .10.18\begin{array}{lcc}& \underline{\text {abor}}& \underline{\text { Machine }}\\\text { Capacity Available } & 16,000 & 20,000 \\\text { Prnduction Standard } & .10 & .18\end{array}
a. What is the percent utilization of the labor capacity in month 4?
b. What is the percent utilization of the machine capacity in month 3?
c. In how many weeks are the labor requirements over capacity?

Correct Answer:

verifed

Verified

a.Labor utilization:
Required capacity =...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents