A Special Project in a Manufacturing Company Has the Following

Question 70

Essay

A special project in a manufacturing company has the following master production schedule MPS) for the next eight weeks:
 Wekk 12345678 Units 7506258009251000900675675\begin{array} { | l | c | c | c | c | c | c | c | c | } \hline \text { Wekk } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\\hline \text { Units } & 750 & 625 & 800 & 925 & 1000 & 900 & 675 & 675 \\\hline\end{array}
The weekly fabrication and welding capacity in (hours) available and production standards in (hours per unit) are:
abor Machine  Capacity Available 7,50010,000 Prnduction Standard 811\begin{array}{lcc}& \underline{\text {abor}}& \underline{\text { Machine }}\\\text { Capacity Available } &7,500 & 10,000 \\\text { Prnduction Standard } &8&11\end{array}

a. What is the percent utilization of the fabrication capacity in week 5?
b. What is the percent utilization of the welding capacity in week 2?
c. In how many weeks are the welding area requirements over capacity?

Correct Answer:

verifed

Verified

a.Fabrication utilization:
Required capa...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents