What is a punch list?
A) It is a list, prepared at the beginning of a renovation project, that identifies for the contractor which jobs are most critical to the renovation's success.
B) It is a list, prepared at the end of a renovation project, which identifies construction work that does not conform to contract specifications.
C) It is a list, prepared by the designer one year after the renovation project is completed, which identifies for the contractor any work that has demonstrated partial or complete structural failure during the year.
D) It is a list, prepared by the contractor at the beginning of the renovation project, which identifies for the hotel owner those portions of the renovation design that do not meet local or national building codes.
Correct Answer:
Verified
Q1: The property's renovation manager should clarify the
Q2: Equipment or materials that are functionally, operationally,
Q3: A good source of sample construction contracts
Q4: Major renovations are usually done on a
Q5: A facility life-cycle cost study is a:
A)set
Q6: Why is it a good idea to
Q7: With a design/build contract:
A)the owner serves as
Q9: Which of the following places the four
Q10: Which of the following estimating methods is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents