Which of the Following Is True Regarding the Internal Rate

Question 112

Multiple Choice

Which of the following is true regarding the internal rate of return for a project?


A) If the internal rate of return is less than the required rate of return, the project will be rejected.
B) If the internal rate of return is equal to the required rate of return, the net present value of the project is zero.
C) If the internal rate of return is more than the required rate of return, the project will be accepted.
D) Managers may believe (in most cases, incorrectly) that the internal rate of return is the compounded rate of return earned by the initial investment.
E) All of these.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents