Which of the following was the result on appeal in the case nugget Bates County Redi-Mix Inc.v.Windler,in which a supplier of concrete sought a mechanic's lien for the cost of concrete although the concrete had to be removed and replaced based upon improper installation by a subcontractor unconnected with the plaintiff?
A) The concrete supplier was granted a mechanic's lien for only 75% of the cost of the concrete.
B) The concrete supplier was granted a mechanic's lien for only 25% of the cost of the concrete.
C) The concrete supplier lost because the concrete had to be replaced.
D) The concrete supplier was granted a mechanic's lien for only 50% of the cost of the concrete.
E) The concrete supplier was granted a mechanic's lien largely because it was not responsible for the improper installation.
Correct Answer:
Verified
Q31: When a person hires a worker to
Q32: Which of the following is true regarding
Q33: What process does a contractor usually have
Q34: Which of the following was the result
Q35: A lien that has priority over other
Q37: Which of the following was the result
Q38: A[n] _ lien is a lien that
Q39: An artisan's lien is a claim on
Q40: Why is it important for a creditor
Q41: A creditor who Pele borrowed money from
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents