Which of the following was the result in Bend Tarp and Liner,Inc. ,v.Bundy,the case in the text in which the plaintiff filed a lien and instituted foreclosure proceedings in connection with a dispute involving payment for a pond liner following the defendant's refusal to pay based on an alleged tear in the liner?
A) That the plaintiff properly installed the liner but was not entitled to foreclose because a section of the wall of the pond collapsed and the liner did not serve the purpose for which it was requested.
B) That the plaintiff installed a defective liner and was not entitled to foreclose.
C) That although the plaintiff had installed a defective liner,the plaintiff was entitled to foreclose because the defendant did not object to the lien within 10 days.
D) That although the plaintiff had installed a defective liner,the plaintiff was entitled to foreclose because the defendant did not object to the lien within 30 days.
E) That the plaintiff properly installed the liner and was entitled to foreclose.
Correct Answer:
Verified
Q29: A creditor has a secured interest in
Q30: Which of the following is true regarding
Q31: When a person hires a worker to
Q32: Which of the following is true regarding
Q33: What process does a contractor usually have
Q35: A lien that has priority over other
Q36: Which of the following was the result
Q37: Which of the following was the result
Q38: A[n] _ lien is a lien that
Q39: An artisan's lien is a claim on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents