Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 4 7 9
B none 3 5 8
C A 2 4 6
D A, B 6 9 9
E C, D 5 5 5
F B 2 5 9
G E, F 3 3 6
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 22 weeks?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q102: Name and describe the three ways to
Q103: Consider a project having the following seven
Q103: Discuss how to develop the critical path
Q104: Consider a project having the following ten
Q107: Consider a project having the following ten
Q108: Consider a project having the following seven
Q110: Consider a project having the following seven
Q111: For the project in question #7 what
Q113: What is involved in the approach for
Q118: Define crashing as it relates to project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents