Consider a project having the following ten activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 7 3,000 6 6,000 1
B A 8 5,000 6 9,000 2
C A 2 2,000 1 3,000 1
D A 4 3,000 4 3,000 0
E B, C 9 4,000 7 6,000 2
F C, D 6 4,000 4 9,000 2
G E 2 3,000 2 3,000 0
H E, F 9 4,000 7 7,000 2
I G 1 4,000 1 4,000 0
J H, I 8 2,000 6 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? by five weeks?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q85: In making a forward pass through a
Q102: Name and describe the three ways to
Q103: Consider a project having the following seven
Q103: Discuss how to develop the critical path
Q106: Consider a project having the following seven
Q107: Consider a project having the following ten
Q108: Consider a project having the following seven
Q111: For the project in question #7 what
Q113: What is involved in the approach for
Q120: What are the benefits of network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents