Consider a project having the following seven activities:
Optimistic Most likely Pessimistic
Immediate Time (o)Time (m)Time (p)
Activity Predecessors (weeks)(weeks)(weeks)
A none 2 3 4
B A 4 4 8
C A 3 5 7
D B 5 5 5
E B, C 3 6 7
F D 4 5 9
G E, F 3 3 7
(a)What is the expected time for each activity?
(b)What is the expected project completion time?
(c)What is the critical path?
(d)What is the variance for each activity?
(e)What are the expected time and variance of each path?
(f)What is the probability that the project will be completed in less than 24 weeks?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q105: Name and describe the three ways to
Q107: What are the characteristics of the critical
Q109: Identify the variables required to predict the
Q114: Consider a project having the following seven
Q114: What are valid reasons for reducing the
Q116: Consider a project having the following ten
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents