Question 114

Essay

Consider a project having the following seven activities:
Normal Normal Crash Crash Maximum
Immediate Time Cost Time Cost Weeks
Activity Predecessors (weeks) ($) (weeks) ($) Reduced
A none 4 3,000 3 5,000 1
B A 9 5,000 7 8,000 2
C A 4 7,000 4 7,000 0
D B, C 6 6,000 4 8,000 2
E C 8 4,000 6 8,000 2
F D 3 4,000 2 9,000 1
G E, F 4 2,000 2 7,000 2
(a)What is the expected project completion time?
(b)What is the critical path?
(c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks?

Correct Answer:

verifed

Verified

(a)26 weeks; (b)A-B-D-F-G; (c)three week...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents