In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late start time for activity L?
A) 13
B) 17
C) 22
D) 33
E) 37
Correct Answer:
Verified
Q29: With probabilistic time estimates for activities, (o)
Q30: Given this information about an activity: ES
Q31: The process of calculating ES and EF
Q32: With probabilistic time estimates for activities, (p)
Q33: Activities on the critical path _.
A) are
Q35: The sum of the activity times on
Q36: In making a forward pass through a
Q37: In making a backward pass through a
Q38: When we are unsure about the duration
Q39: Given this information about an activity: ES
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents