In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T?
A) the smallest LS for the three activities that activity T immediately precedes
B) the largest LS for the three activities that activity T immediately precedes
C) the smallest LF for the three activities that activity T immediately precedes
D) the largest LF for the three activities that activity T immediately precedes
E) the activity time for activity T
Correct Answer:
Verified
Q32: With probabilistic time estimates for activities, (p)
Q33: Activities on the critical path _.
A) are
Q34: In making a backward pass through a
Q35: The sum of the activity times on
Q36: In making a forward pass through a
Q38: When we are unsure about the duration
Q39: Given this information about an activity: ES
Q40: The last project activity ES and LS
Q41: There are four activities on the critical
Q42: What can be used to display graphically
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents