In Making a Backward Pass Through a Network, Activity T

Question 37

Multiple Choice

In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T?


A) the smallest LS for the three activities that activity T immediately precedes
B) the largest LS for the three activities that activity T immediately precedes
C) the smallest LF for the three activities that activity T immediately precedes
D) the largest LF for the three activities that activity T immediately precedes
E) the activity time for activity T