Dem Mfg. has gathered the following data in preparing to record their direct labour payroll costs for the week: Actual hours worked 18,500
Standard hours allowed 20,000
Total direct labour variance $8,300 F
Direct labour price variance $3,700 U
The actual direct labour costs were:
A) $144,300
B) $148,000
C) $160,000
D) $151,700
Correct Answer:
Verified
Q87: Everett, Inc. budgeted $1,488,000 for total overhead.
Q92: Everett, Inc. budgeted $1,488,000 for total overhead.
Q96: Everett, Inc. budgeted $1,488,000 for total overhead.
Q97: Everett, Inc. budgeted $1,488,000 for total overhead.
Q105: White, Inc. produces a chemical product whose
Q106: During the period Richeleau produced 1,000 units
Q108: During the period Richeleau produced 1,000 units
Q111: The difference between actual capacity used and
Q112: During the period Richeleau produced 1,000 units
Q118: White, Inc. produces a chemical product whose
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents