During the period Richeleau produced 1,000 units of product. The flexible budget for standard costs is: Direct materials $43,000
Direct labour 67,000
Variable overhead 30,000
Fixed overhead 25,000
Variances for the period are:
Direct materials price $ 400 U
Direct materials efficiency 500 F
Direct labour price 600 F
Direct labour efficiency 200 U
Variable overhead spending 300 F
Variable overhead efficiency 100 F
Fixed overhead spending 500 F
Fixed overhead production volume 1,000 U
The actual cost of direct labour incurred was:
A) $66,200
B) $66,400
C) $66,600
D) $67,400
Correct Answer:
Verified
Q92: Everett, Inc. budgeted $1,488,000 for total overhead.
Q96: Everett, Inc. budgeted $1,488,000 for total overhead.
Q97: Everett, Inc. budgeted $1,488,000 for total overhead.
Q105: White, Inc. produces a chemical product whose
Q106: During the period Richeleau produced 1,000 units
Q107: Dem Mfg. has gathered the following data
Q111: The difference between actual capacity used and
Q112: During the period Richeleau produced 1,000 units
Q113: Dem Mfg. has gathered the following data
Q118: White, Inc. produces a chemical product whose
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents